Code | Description | Unit of Measure |
---|---|---|
200 | Place pole 25' to 55' | ea. |
204 | Remove pole or push brace any size- Includes pulling the pole, filling and tamping the hole. Hauling the pole to a pole/yard pile in the vicinity. It also includes removal of all hardware and stenciling on old pole. | ea. |
211 | Place anchor all locations - includes hauling anchor to job site and all required work to properly install anchor in correct position and proper depth. Includes screw/expanding type anchors | ea. |
212 | Remove anchor and rod - Removal of the anchor/rod out of the ground, all restoration as required, and haul anchor/rod to designated storage area | ea. |
220 | Place/remove guy (all types and all sizes) - Includes the hauling of all required materials and associated hardware, boring any necessary holes, placing and removing bolts and making up/removing or re-tensioning guy. (this includes guy guard, span guys, sidewalk guys, overhead guys and down guys) | ea. |
222 | Transfer drop - To transfer aerial wire from pole, crossarm, building or messenger and attach to another pole, crossarm, building or messenger strand. This will include any guards, cleats and associated hardware as required. | ea. |
223 | Lower/raise drop - Lower or raise drop on any pole or building as required by engineering work order | ea. |
230 | Transfer strand/cable attachment without guy - single attachment | ea. |
231 | Transfer strand/cable attachment with guy - single attachment | ea. |
232 | Lower or raise strand/cable attachment without guy - single attachment | ea. |
233 | Lower or raise strand/cable attachment with guy - single attachment | ea. |
234 | Transfer buried riser - transfer buried riser cable on pole, includes cable guards | ea. |
250 | Place strand (all sizes) | per ft |
251 | Lash copper cable - 100 pr and less | per ft |
252 | Lash copper cable - 101 pr up to 400 pr | per ft |
254 | Lash fiber all sizes | per ft |
256 | Remove strand/cable and fiber - this unit includes removal of strand and lashed facilities to that strand. It includes removal of all hardware from poles associated with the stripped facilities. Also returning all removed facilities back to the appropriate CCI facility | per ft |
257 | Snow Shoes - Place individual snow shoe | ea. |
258 | Snow Shoes - Place pair snow shoes to store fiber properly on strand | per pr |
260 | Place self-support and flat drop cable….includes 12 fiber both flat and self support . Also includes both 6 pair and 12 pair copper drop | per ft |
261 | Remove self-support drop cable….same definition as above | per ft |
264 | Resag strand/cables when pulled down | per ft |
265 | Delash and then relash a section when lashing wire has been broken (manager approval needed) | per ft |
Code | Description | Unit of Measure |
---|---|---|
347 | Pull fiber in conduit | per ft |
353 | Mandrel duct and install pull wire - This operation applies to mandrelling ducts at the request of the customer to determine the condition of the duct. | per ft |
Code | Description | Unit of Measure |
---|---|---|
506 | Hourly 2 person Linecrew with Line truck ( regular time) | hourly |
507 | Hourly 2 person Linecrew with Line truck ( over time) | hourly |
508 | Line technician (regular time) | hourly |
509 | Line technician (overtime) | hourly |
512 | MH Entry - to include test pump and ventilate as well as to provide tools equipment to safely enter and work in a manhole…..***If working the same MH consecutive days or nights then only 1 time can this be taken, not to be used for each crew when changing shifts | ea. |
517 | Dump truck (single axle) | hourly |
519 | Line truck with auger & boom | hourly |
521 | Cable trailer (all sizes) | hourly |
523 | Pole-sand trailer | hourly |
555 | Bucket Truck | hourly |
Code | Description | Unit of Measure |
---|---|---|
201 | Place pole 25' to 55' Off road-dirt | ea. |
202 | Place push brace pole, any size | ea. |
203 | Set pole in rock….Unit add-on for setting in rock | ea. |
205 | Pole/relocation - Relocation is used when a pole is lifted and moved over by trenching/lifting the pole out of a present location and placing in a new hole at an adjacent location. Also included is setting the pole plumb or at the correct angle of rake, proper tamping, tagging and restoring the area to an orderly appearance. | ea. |
206 | Straighten pole - This applies to existing poles only. Includes loosening the dirt around a pole, replumbing the pole, tamping and restoration to a neat appearance. | ea. |
209 | Stencil pole when that is the only required step for that pole location - Means placing the required stenciling on existing poles to make it coincide with continuing property records. This includes removing old stencils when necessary to re-number a pole. Poles are to be numbered as required when set. This unit is only to be used if a no other work is to be performed at the pole and the EWO is calling to stencil a pole. | ea. |
213 | Place rock bolt anchor | ea. |
221 | Place ground rod - This unit includes hauling the ground rods to the work location and installing, either mechanically or manually, the total number of rods required to obtain the ground as indicated on the work drawing. Also includes cleat ground wire as needed. | ea. |
224 | Place/remove extension arm - placement of cable extension arms to clear obstacles | ea. |
225 | Attach cable to pole or building (Fiber and Cable) - This covers all work necessary to cleat cable, drop to walls, backboards, and riser poles according to Customer specifications. | per ft |
226 | Place/Remove "U" cable guard - making sure cable or fiber is properly cleated up pole or building | ea. |
235 | Transfer foreign utilities - This unit applies to transferring or swinging of foreign utilities (CATV etc.) only with prior approval | ea. |
236 | Transfer or move PMT (Pole Mount Terminal) - when not transferring strand or cable at the same location | ea. |
240 | Place large apparatus - Includes placement of large apparatus such as fiber FDH's, load coils, air dryers or cross connect boxes. Also covers hauling the apparatus and required mounting hardware from the storage location to the job site and properly mounting on pole or strand. | ea. |
241 | Remove large apparatus - applies to removal of apparatus from pole or strand after it has been un-spliced from the cable and the hauling to a designated area. | ea. |
242 | Transfer large apparatus - Includes placement/transfer of large apparatus such as fiber FDH's, load coils, air dryers or cross connect boxes. Also covers hauling the apparatus and required mounting hardware from the storage location to the job site and properly mounting on pole or strand. | ea. |
253 | Lash copper cable - 401 pr and greater | per ft |
255 | Place fiber marker tags - on existing route NOTE: UNIT 254 IS TO BE UTILIZED ON EXISTING ROUTES WHEN CALLED FOR ON EWO BY ENGINEERING. NEW CABLE PLACEMENT INCLUDES PLACEMENT OF MARKER TAGS. | ea. |
262 | Place self supporting inner duct | per ft |
263 | Remove self supporting cable/inner duct | per ft |
Code | Description | Unit of Measure |
---|---|---|
303 | Machine trench to 24" | per ft |
304 | Machine trench to 30" | per ft |
305 | Machine trench to 36" | per ft |
306 | Backhoe to 24" | per ft |
307 | Backhoe for every foot over 24" | per ft |
308 | Hand dig to 24" | per ft |
309 | Hand dig for every foot over 24" | per ft |
312 | Place cable/innerduct to 2" in trench dug by others | per ft |
313 | Place cable/innerduct over 2" in trench dug by others | per ft |
314 | Place additional cable/innerduct to 2" same time | per ft |
315 | Place additional cable/innerduct over 2" same time | per ft |
316 | Place up to 2" PVC in open trench (each) | per ft |
317 | Place over 2" PVC in open trench (each) | per ft |
318 | Slick bore - covers hauling the pipe to the job site, supplying and using all necessary tools and equipment, all required digging in connection with the operation and installing the pipe where required by pushing pipe | per ft |
325 | Place ground rod and wire - this unit will cover hauling #6 ground wire & ground rod to the job site, burying by any method at the required depth, and placing ground wire & rod into the pedestal or cabinet. | ea. |
326 | Install warning tape | per ft |
327 | Backfill trench dug by others - Includes backfill of trench dug by others up to 3' deep and 6" wide. | per ft |
328 | Place or remove pedestal 8"and smaller - includes hauling materials to the job site and the placing of any above ground fixtures used for enclosing or terminating buried or trenched cable. The work operation includes the placing of all parts of the fixture (mounting brackets, etc.) which are required at any one location, and also includes the feeding of cable properly into the fixture | ea. |
329 | Place or remove pedestal over 8" - includes hauling materials to the job site and the placing of any above ground fixtures used for enclosing or terminating buried or trenched cable. The work operation includes the placing of all parts of the fixture (mounting brackets, etc.) which are required at any one location, and also includes the feeding of cable properly into the fixture | ea. |
330 | Raise or lower pedestal 8" and smaller | ea. |
331 | Raise or lower pedestal over 8" | ea. |
332 | Place sign post and associated signs - This unit includes all labor and equipment associated with placing/removing cable warning posts and signs | ea. |
335 | Place X-Conn box - Includes hauling cross-connect box to job site, placement of the box on the pad, cable stubs, and attachment of all anchor bolts to the mounting hardware | ea. |
341 | Pull 100 pr or less in conduit | per ft |
342 | Pull 101-400 pr in conduit | per ft |
343 | Pull 401-900 pr in conduit | per ft |
344 | Pull 901 pr and over in conduit | per ft |
345 | Pull innerduct in conduit (each) | per ft |
346 | Pull Maxcell in conduit (each) - Permission needed | per ft |
349 | Place tracer wire - This unit to be used when NOT placing fiber optic cable. | per ft |
350 | Remove underground cable up to 600pr - This covers all work operations necessary to remove cable from the duct systems between manholes or from direct buried duct and plugging the ducts after the cable has been removed. | per ft |
351 | Remove underground cable over 601pr - This covers all work operations necessary to remove cable from the duct systems between manholes or from direct buried duct and plugging the ducts after the cable has been removed. | per ft |
352 | Remove underground fiber cable - This covers all work operations necessary to remove cable from the duct systems between manholes or from direct buried duct and plugging the ducts after the cable has been removed. | per ft |
354 | Remove innerduct - this covers all work operations necessary to remove innerduct from duct systems between manholes or from direct buried duct | per ft |
355 | Place fiber handhole - this includes all equipment required for hauling the splice box/hand hole from the storage facility to the job site, all excavating and placement of the splice box/handhole at the required depth. Includes termination and sealing conduits, back filling the excavation and placing the proper amount of cover over the box when requested | ea. |
356 | Place handhole up to 4x8x4 - this includes all equipment required for hauling the splice box/hand hole from the storage facility to the job site, all excavating and placement of the splice box/handhole at the required depth. Includes termination and sealing conduits, back filling the excavation and placing the proper amount of cover over the box when requested | ea. |
361 | Core bore facility wall - This includes the furnishing of all equipment and labor necessary to core bore a hole through the concrete wall of a central office vault or manhole for the purpose of installing cable, load coil stubs, conduit, etc. | ea. |
Code | Description | Unit of Measure |
---|---|---|
500 | Equipment operator (regular time) | hourly |
501 | Equipment operator (overtime) | hourly |
502 | Foreman (regular time) | hourly |
503 | Foreman (overtime) | hourly |
504 | Laborer (regular time) | hourly |
505 | Laborer (overtime) | hourly |
510 | Splice Technician (regular time) | hourly |
511 | Splice Technician (overtime) | hourly |
513 | Pickup truck | hourly |
514 | Combo truck - jack hammer, concrete chipping tools, hand tools generator and cords, MH set up including ventilation equipment and gas test meter, 800' - 1/2" fiberglass rodder, 400' - 1/4" fiberglass rodder, 2" water pump, vacuum, safety equipment including traffic control sign packages....***expect all trucks to come properly outfitted with all required to get the job done | hourly |
515 | Truck (flat bed) | hourly |
516 | Truck (2 ton & over) | hourly |
518 | Dump truck (double axle) | hourly |
520 | Semi-tractor w/low boy trailer | hourly |
522 | Equipment trailer | hourly |
524 | Front end loader | hourly |
525 | Bulldozer w/static plow (any size) | hourly |
526 | Trencher or cable plow (1-40 horsepower) | hourly |
527 | Trencher or cable plow (over 40 horsepower) | hourly |
528 | Air compressor - tow behind | hourly |
529 | Vibrator tamper (compactor or wheeled) | hourly |
530 | Vibrator tamper (hand-held) | hourly |
531 | Tractor equipped with bushhog | hourly |
532 | Water pump (centrifugal) | hourly |
533 | Water pump (mud hog) | hourly |
534 | Wheeled Road Saw | hourly |
535 | Manhole blower | hourly |
536 | Cut-Off Saw | hourly |
537 | Portable generator | hourly |
538 | Core Drill includes bit up to 4-1/4" | hourly |
539 | Chain saw | hourly |
540 | Concrete saw | hourly |
541 | Asphalt roller | hourly |
542 | Tree trimming truck | hourly |
543 | Chipper | hourly |
544 | Flasher barricades | hourly |
545 | Roadway directional flashing signal | hourly |
546 | Sm-Med Excavator up to 12K lb. | hourly |
547 | Backhoe | hourly |
548 | LRG Excavator over 12K lb. | hourly |
549 | Trackhoe | hourly |
550 | Track dozer (small) | hourly |
551 | Grader | hourly |
552 | Welder w/ truck and tools | hourly |
553 | 1000 watt light bank | hourly |
554 | Trench Box | hourly |